ONEOK to expand refined products pipeline to greater Denver area

July 18, 2024
ONEOK plans to expand its pipeline capacity connecting Mid-Continent and Gulf Coast refined products supply with the greater Denver area to meet growing demand and increase connectivity with Denver International Airport.

ONEOK Inc., Tulsa, Okla., plans to expand its pipeline capacity connecting Mid-Continent and Gulf Coast refined products supply with the greater Denver area to meet growing demand and increase connectivity with Denver International Airport (DIA).

The project—expected to cost $480 million and be completed in mid-2026—includes construction of a new 230-mile, 16-in. OD pipeline from Scott City, Kan., to DIA and the addition or upgrading of certain pump stations along the existing refined products pipeline system, the company said in a release July 18. Total system capacity will increase by 35,000 b/d and will have additional expansion capabilities.

Following the close of an open season earlier this year, the project is fully subscribed under long-term contracts.