*Designates projects listed for the first time.
UNITED STATES
CENEX FARMERS UNION. Laurel, Mont. Sulfur recovery unit upgrade. Completion: Mid-1994.
CITIZENS GAS. Indianapolis, Ind. 7 t/d sulfur unit under construction. PD/Engr/DD/PE/CS: Krupp Koppers. Completion: 1994.
COASTAL REFINING & MARKETING. Corpus Christi, Tex. 115 mt/d expansion of claus unit. Contr: Ford, Bacon & Davis. Completion: 4th Qtr. 1994.
Westville, N.J. 20 mt/d Claus unit. Engr: Ford, Bacon & Davis. Completion: 4th Qtr. 1995.
EXCEL PARALUBES. Lake Charles, La. *2-90 t/d sulfur plants in design stage. (joint venture of Conoco and Pennzoil). Completion: 1997.
GOLDSTON OIL Corp. Gilmer, Tex. *8 t/d CBA sulfur recovery unit in engr. stage. PD/Engr: Ortloff Engineers Ltd. Completion: 1995.
KOCH REFINING. Corpus Christi, Tex. 75 t/d sulfur recovery tail gas treating unit in engr. stage. PD/Engr/DD/PE: Pritchard. Completion: 1995.
LION OIL Co. Eldorado, Ark. *80 t/d Claus Sulfur recovery unit, SCOT Tailgas treater in detailed design stage. Contr: Ortloff Engineers Ltd., The Pro-Quip Corp. Completion: 1995.
LYONDELL-CITGO REFINING Co. Ltd. Houston, Tex. 235 mt/d modified Claus & tail gas treating unit from refinery offgas. Contr: Pritchard. Completion: 1996.
MARATHON PETROLEUM Co. Robinson, Ill. 2-90 t/d sulfur recovery unit. PD: Parsons.
MAXUS EXPLORATION. Sunray, Tex. 14 t/d Superclaus unit in engr. stage. PD: Comprimo. Completion: 1994.
MOBIL OIL. Coden, Ala. *Expansion of gas treating and sulfur recovery under construction. Contr: ABB Randall Corp. Completion: 4 t" Qtr. 1994.
MURPHY OIL Corp. Meraux La. *80 t/d Claus sulfur recovery unit, SCOT tailgas treater under construction. Contr: Ortloff Engineers Ltd., The Pro-Quip Corp.
PHILLIPS PETROLEUM. Borger Tex. 120 t/d Claus unit to replace existing 80 t/d unit in engr. stage. Completion: 1" Qtr. 1996.
SHELL OIL Co. Deer Park, Tex. 2-135 t/d sulfur recovery tail gas treating units under construction. PD/Engr/DD/PE: Pritchard. Completion: 1994.
Martinez, Calif. 300 t/d sulfur recovery, tail gas treating unit in engr. stage. PD/Engr/DD/PE: Pritchard. Completion: 1996.
UNO-VEN Co. Lemont, Ill. 21 t/d revamp of sulfur unit. Engr: H-R International.
ABU DHABI
ABU DHABI NATIONAL OIL Co. 3-600 t/d sulfur recovery units in engr. stage. Engr/DD/PE: Pritchard. Completion: 1996.
Habshan. new sulfur recovery unit in engr. stage. CS: Bechtel. Completion: 4th Qtr. 1995.
Ruwais. expansion of sulfur recovery unit planned. Completion: 1995.
BELGIUM
PETROFINA. Antwerp. 400 t/d Claus unit in engr. stage. PD: Comprimo. Completion: 1994.
BRAZIL
PETROBRAS. Canoas, RS. 70 mt/d Claus unit (from refinery) process design stage. Contr: Staff. Completion: 1998.
Cubatao, SP. 2-35 mt/d Claus unit (from refinery) under construction. Contr: Staff. Completion: 1996.
Paulinia, SP. 106 mt/d sulfur unit in process design stage. Completion: 1997.
Araucaria. *65 t/d sulfur unit planned. Lic: Staff. Completion: 1999.
CANADA
MOBIL OIL CANADA. Carstairs, Alta Sulfur recovery unit. Superclaus-99 process.
WESTCOAST ENERGY. Chetwynd, B.C. 965 t/d sulfur recovery unit expansion in engr. stage. PD/Engr/DD/PE: Delta Catalytic Engr. and Const. Completion: 1994.
CHINA
DALIAN WEST PACIFIC PETROCHEM CO. Dalian. 24.5 MMcfd Clauspol unit in engr. stage. Engr: Gaz Integzale. Completion: 1995.
TANGSHAN MUNICIPAL COKING PLANT. Tangshan. 4 t/d sulfur plant in the engr. stage. PD/Engr/PE/CS: Krupp Koppers. Completion: 1995.
QINGDAO GAS WORKS. Qingdao. 4 t/d mt/y sulfur unit in engr. stage. PD: Krupp Koppers. Completion: 1995.
CHINA, TAIWAN
CHINA STEEL Corp. Kaosiung. 19 t/d sulfur plant under construction. PD/Engr/PE/CS: Krupp Koppers. Completion: 1994.
COLOMBIA
ECOPETROL. Barrancaberaeja. 30 t/d sulfur recovery unit under construction. PE/Engr/PD/CS: Tecnologie Progetti Lavori. Completion: April 1995.
COMMONWEALTH OF INDEPENDENT STATES
(formerly the U.S.S.R,)ATYRAU REFINERY. Atyrau, Kazakhstan. *1 0.000 t/y sulfur production with MEA regeneration planned. Contr: Hydrocarbon Engineering.
MAGNITOGORSK IRON & STEEL WORKS. Magitogorsk. 22 t/d sulfur unit in the engr. stage. PD/Engr/PE/CS: Krupp Koppers. Completion: 1995.
ODESSA REFINERY. Odessa, Ukraine. 22 t/d sulfur recovery unit under construction. Contr: CTIP. Completion: 1994.
COSTA RICA
REFINADORA COSTA. Limon. 425 Mscfd sulfur recovery unit in engr. stage. PD/DD/PE/CS: Dragados. Completion: 1995.
CZECH REPUBLIC
PARAMO PARDUBICE REFINERY. Pardubice. *10 t/d sulfur unit in engr. stage. Const: KTI. Completion: 1995.
FRANCE
RAFF. DU SUD OUEST. Collombey. 6 t/d sulfur recovery in engr. stage. PD/Engr/CS/PE: Comprimo. Completion: 1994.
GERMANY
BEB ERDGAS. Grossenkneten. Scot treater in engr. stage. PD/Engr/PE/CS: Comprimo. Completion: 1994.
OMV. Karlsruhe. 2-225 t/d oxygen Claus/Scot unit in engr. stage. PD/Engr: Lurgi. Lic: Shell/Comprimo/Lurgi. Completion: 1994.
PCK AG. Schwedt. 240 t/d expansion of sulfur recovery unit in engr. stage. Engr/PE/CS: Comprimo By. Completion: End 1994.
VEBA. Gelsenkirchen. 70 Vd Claus/Scot unit in engr. stage. Lic: Shell/Comprimo/Lurgi. Engr/PD/DD/PE: Lurgi. Completion: 1994.
HELLENIC ASPROPYRGOS REFINERY. Athens. 40 mt/d H2S rich gas recovery. In engr. stage. Superclaus/Comprimo process. Lic: Comprimo. PD/Engr/DD/PE/CS: TPL. Completion: 4th Qtr. 1995.
MOTOR OIL HELLAS. Corinth. 10 t/d sulfur recovery unit expansion in engr. stage. PD/Engr/PE/CS: Tecnologie Progetti Lavori. Completion: June 1995.
INDIA
MANGALORE REFINING & PETROCHEMICALS. Mangalore. *36.5 t/d sulfur unit under construction. Lic: KTI/Unocal. Const: KTI. Completion: 1995.
IRAN
NATIONAL IRANIAN OIL Co. Bandar Abbas. 130 mt/d sulfur recovery plant under construction. DD/PD/CS/PE: Snamprogetti. Completion: 1995.
21 0 Vd Claus unit under construction. PD/Engr: Comprimo. Completion: 1994.
ITALY
AGIP PETROLI. Sannazzaro. *60 t/d new sulfur purisol, oxygen claus in engr. stage. Lic/PD: Lurgi 01-Gas-Chemie GmbH. Completion: 1996.
*160 t/d revamp of sulfur claus to oxygen claus in engr. stage. Lic/PD: Lurgi 01-Gas-Chemie GmbH. Completion: 1995.
AGIP RAFFINAZIONE. Taranto. 150 t/d Scot unit in engr. stage. PD: Comprimo. Completion: 1994,
CAMELI PETROLI. Mantova. *40 t/d sulfur unit expansion. Contr: KTI. Completion: 1994.
ISAB SPA. Priolo Gargallo. *95 t/d sulfur unit. Contr: KTI. Completion: 1996.
JAPAN
KOA OIL Co. Ltd. Marifu. 140 t/d Scot treater in engr. stage. PD: Comprimo. Completion: 1994,
JORDAN
JORDAN PETROLEUM REFINERY. Zerka. 18 mt/d Claus unit from refinery gases. $4.5 MM. Completion: 1997.
KOREA
LUCKY Ltd. sulfur recovery unit in engr. stage. PD/DD/Engr/PE: Linde.
MALAYSIA
MALAYSIAN REFINING Co. *sulfur recovery unit in engr. stage. Engr/PD: Foster Wheeler. Completion: 1998.
MARTINIQUE
TOTAL. sulfur recovery unit in engr, stage. Engr/DD/PE/CS: Foster Wheeler Conception Etudes Entretien. Completion: 1" Qtr. 1995.
MEXICO
PEMEX. Tula, Hgo. 40 Vd Claus unit from refinery gas in engr. stage.
Cadereyta. *40 t/d Claus unit from refinery gas under construction.
Salina Cruz. *40 t/d Claus unit from refinery gas under construction.
NETHERLANDS
KUWAIT PETROLEUM. Rotterdam. 70 V d Superclaus revamp in engr. stage. PD/Engr/PE/CS: Comprimo. Completion: 1994.
SHELL NEDERLAND. Pernis. 440/625 t/d Claus/Scot units in engr. stage. PD/Engr/PE/CS: Comprimo. Completion: 1997.
PHILIPPINES
PHILIPINAS SHELL PETROLEUM Corp. Tabangao. 90 t/d sulfur recovery unit. Completion: Mid-1994.
SAUDI ARABIA
ARAMCO. 300 t/d sulfur recovery unit. PD/Engr: Parsons. Completion: 4th Qtr. 1994.
SINGAPORE
SHELL EASTERN. Pulau Bulkum. 365 t/d Claus revamp in enr. stage. PD/Engr/PE/CS: Comprimo. Completion: 1994.
125 t/d Claus unit in engr. stage. PD/Engr/PE/CS: Comprimo. Completion: 1994.
SINGAPORE REFINING Co. Pulau Merlimau. 80 t/d Claus unit in engr. stage. PD: Comprimo. Completion: 1995.
*45 t/d new spent acid regeneration unit under construction. Contr: JC Corp. Tokyo/Simon-Carves Ltd. Completion: 1994.
SPAIN
ELCOGAS. Puertollano. 53 t/d sulfur unit in the engr. stage. PD/Engr/DD/PE/CS: Krupp Koppers. Completion: 1996.
PETRONOR. Somorrostro. 86 t/d sulfur recovery unit under construction. Engr/DD/PE: Tecnicas Reunidas. Completion: 1994.
REPSOL PETROLEO. La Coruna. 144 mt/d sulfur unit in engr. stage. $25 MM. DD/Engr: John Brown, PD: Comprimo. Completion: 1994.
Cartagena. 35 t/d sulfur unit.
Puertollano. 2-47.5 mt/d Comprimo unit in engr. stage. Engr/DD/PE: Tecnicas Reunidas. PD: Comprimo. Completion: 1994.
TRINIDAD
TRINIDAD & TOBAGO OIL Co. Ltd. Pointe-A-Pierre, 150 mt/d new Super-claus unit from H2S- PD: Comprimo B.V, Completion: 4th Qtr. 1994.
TURKEY
TURKISH PETROLEUM REFINERIES Corp. Izmit. 90 mt/d Claus and tail gas unit (from refinery gas) under construction. Contr: Snamprogetii/Tekfen. Completion: 1997.
*47 Vd Claus sulfur recovery unit from acid gas expansion.
Izmir. *40 t/d Claus sulfur recovery unit from process gas expansion.
'73 t/d Claus sulfur recovery unit from process gas expansion.
Kirikkale. *23 t/d Claus sulfur recovery unit from acid gas expansion.
*60 Vd Claus sulfur recovery unit from acid gas expansion.
VENEZUELA
MARAVEN, Cardon. 230 mt/d Claus unit in the engr. stage. Engr/Contr: /Bechtel/Jantesa/Comprimo. $7.6 MM. Completion: 4th Qtr. 1995.