Gazprom, RusGasDobycha advance Ust-Luga LNG-chemical project
PJSC Gazprom and RusGasDobycha are moving forward with plans for construction of their previously announced natural gas liquefaction and processing complex on the Gulf of Finland near the seaport of Ust-Luga, Leningrad Oblast, Russia (OGJ Online, Apr. 2, 2019).
As of mid-May, the partners have completed agreements for basic design of the project, as well as specifications for feedstock and commercial products to be produced at the proposed complex, Gazprom said.
With RusKhimAlyans—a 50-50 special-purpose venture of Gazprom and RusGazDobycha that will act as project operator—now issued technical specifications for connecting the complex to Gazprom’s gas transmission system, the partners also have started drafting design documentation, as well as fully completed engineering surveys at the construction site, which is currently being cleared and prepared for construction works.
While efforts remain under way to attract financing from Russian and international credit institutions for the more than 700 billion-rubles project, Gazprom said the partnership, by yearend 2020, will still proceed with submitting project design documentation for regulatory approval, place orders for long-lead equipment, and select an engineering, procurement, and construction (EPC) contractor for the complex’s gas processing units and off-site installations.
The partnership also plans to award a contract for project management consultancy (PMC) by yearend, Gazprom said.
Using a feedstock of wet natural gas produced from Gazprom’s Achimov and Valanginian deposits in the Nadym-Pur-Taz region of the Yamal Peninsula, the proposed RusKhimAlyans complex will process 45 billion cu m/year of gas to yield 13 million tonnes/year of LNG, as much as 4 million tpy of ethane, and more than 2.2 million tpy of LPG.
While LNG and LPG produced at the complex will be exported, ethane from the site will feed nearby RusGazDobycha subsidiary Baltic Chemical Complex LLC’s (BCC) proposed $13-billion ethane cracking project, which—once in operation—will produce more than 3 million tpy of polymers (OGJ Online, Nov. 18, 2019).
About 20 billion cu m/year of residual gas from the RusKhimAlyans complex will flow into Gazprom’s gas transmission system.
Gazprom said commissioning of the RusKhimAlyans and BCC complexes will be synchronized, with the first trains scheduled for startup during fourth-quarter 2023 and the second trains to follow in fourth-quarter 2024.
Robert Brelsford | Downstream Editor
Robert Brelsford joined Oil & Gas Journal in October 2013 as downstream technology editor after 8 years as a crude oil price and news reporter on spot crude transactions at the US Gulf Coast, West Coast, Canadian, and Latin American markets. He holds a BA (2000) in English from Rice University and an MS (2003) in education and social policy from Northwestern University.