Venture Global CP2 awards Phase 1 EPC contract to Worley
Venture Global CP2 LNG LLC has awarded Worley an engineering, procurement, and construction (EPC) contract for the 10-million tonne/year (tpy) Phase 1 of its 20-million tpy CP2 LNG plant in Cameron Parish, La. Worley will provide full EPC execution, including commissioning and start up.
Full notice to proceed with construction will follow Venture Global taking final investment decision on the project. The company expects to start construction in 2023, pending receipt of US Federal Energy Regulatory Commission (FERC) authorization, which is under way.
CP2 would be Venture Global’s third plant, the company targeting a second-quarter 2026 in-service date (OGJ Online, Jan. 23, 2023). The plant will use the same modular construction used at Venture Global’s 10-million tpy Calcasieu Pass LNG, each phase consisting of 18 small liquefaction trains installed as nine two-train blocks (OGJ Online, Apr. 29, 2022).
CP2 will also include four 200,000-cu m full-containment LNG storage tanks. The 85.4-mile, 48-in. OD CP Express pipeline will carry natural gas to the 6-mile, 24-in. OD Enable Gulf Run Lateral for delivery to CP2. Both pipelines are part of the overall project awaiting FERC approval.
Christopher E. Smith | Editor in Chief
Christopher brings 27 years of experience in a variety of oil and gas industry analysis and reporting roles to his work as Editor-in-Chief, specializing for the last 15 of them in midstream and transportation sectors.