CNOOC starts production from Dongfang 29-1 field
Jan. 21, 2025
CNOOC Ltd. has started production from the Dongfang 29-1 gas field development project in the Yinggehai basin with an average water depth of about 68 m.
The main production infrastructure includes a new unmanned wellhead platform and a submarine pipeline. A total of 6 development wells are planned to be commissioned. The project is expected to achieve a peak production of 38 MMcfd of natural gas in 2025.
The oil and gas produced will be connected to the existing infrastructure of Dongfang gas fields through a subsea pipeline for processing.
CNOOC is operator of the project with 100% interest.