*Designates projects listed for the first time in the Journal.
UNITED STATES
AMERADA HESS. Tiogaa, N.D. expansion of treating facility under construction.
AMOCO. Ulysses, Kan. natural gas processing plant in the engineering stage. $80 MM. Engr: Flour Daniel. Completion: 1992 Chocolate Bayou, Tex. polypropylene plant in the engineering stage. $56 MM. Design/Engr: John Brown. Completion: 1992.
ARCO ALASKA, Inc. Prudhoe Bay, Alas. 2,400 MMscfd gas handling facilities reinjection expansion in the engineering stage. $1.1 billion. Design/Engr: Parsons. Contr: Fluor Daniel. Completion: 4th Qtr. 1994.
BP OIL Co. Belle Chasse, La. 40,000 b/d expansion of treating facility in the engineering stage. Contr: Howe-Baker Engr. Completion: 1992.
EXXON Co. Mobile Bay, Ala. 300 MMscf/d sour gas treatment plant under construction. Contr: Zachry. Completion: June 1993.
Santa Barbara, Calif. *20 MMscfd gas processing plant with 230,000 g/d of NGL. Completion: May 1994.
MAXUS ENERGY Corp. Moore Co., Tex. 160 MMcfd natural gas processing plant. Cryogenic expander. Contr: Randall. Completion: January 1993.
MESA, Inc. Satanta, Kan. 190 MMscfd nitrogen rejection plant in fabrication phase. $43 MM. Engr: Process System Int/ABB Randall. Design/Procurement/Const: ABB Randall. Completion: June 1993.
MOBIL. Beaumont, Tex. 4 new units and 5 revamps to improve C5, reformate in the engineering stage. Engr/Contr: Kellogg. 1992.
PANHANDLE EASTERN Corp. Liberal, Kan. $25 MM upgrade to extract 800 MMcf/year of crude helium and additional propane. (Joint venture with Air Products & Chemicals Inc.).
PHILLIPS PETROLEUM Co. Kenai. Alas. modify plant capacity. Process/Design: Bechtel. Contr: UFCO, Inc. Completion: December 1992.
*Expansion of LNG plant under construction. $20 MM Engr/Contr: Bechtel/Becon. Completion: 2nd Qtr. 1993.
UNOCAL, Moab, Utah. expansion of the Lisbon plant under construction. Contr: Fish Engr. Completion: 1992.
VALERO NATURAL GAS PARTNERS LP. Thompsonville, Tex. 200 MMcfd turboexpander gas processing plant planned. 420,000 g/d of NGL. $30.9 MM. Completion: January 1993.
WARREN PETROLEUM Co. Mt. Belvieu, Tex. *butane plant in the engineering stage. $50 MM. Design/Engr: John Brown. Completion: 1992.
YUKON PACIFIC. Anderson Bay, Alas. 2,000 MMscfd LNG plant in the engineering stage. Engr: Bechtel. Completion: 3rd Qtr. 1997.
ABU DHABI
ABU DHABI GAS INDUSTRIES. BuHasa. Upgrade of second gas processing train. Contr: Stone & Webster. Completion: Mid-1992.
Jarn Yaphour. 1.6 MM Ncu m/d gas gathering and conditioning plant under construction. Design/Proc. Engr/Contr: Snamprogetti. Completion: 1993.
ABU DHABI MARINE. Umm Shelf field 600 MMscfd gas plant expansion in the engineering stage. Engr/Contr: Bechtel. Completion: 4th Qtr. 1993.
ALGERIA
SONATRACH. Bethioua near Arzew. 1,000 MMcfd revamp LNG2 natural gas liquefaction complex in the engineering stage. Engr/Contr/Lic: Kellogg. Completion: 1994.
*(Joint venture with Air Products and Chemicals and L'Air Liquide) recover, purify, and liquefy 600 MMcf/year of liquid helium and 100 t/d of nitrogen from tail-gases of LNG natural gas liquefaction facility. Completion: 1993.
Guellala. 500 mt/d LPG recovery plant under construction. Contr: Mitsubishi. Completion: December 1992.
Hamra. 15 MM Scu m/d gas gathering and conditioning plant under construction. Design/Proc. Engr/Contr: Snamprogetti. Completion: 1994.
Hassi Messaoud Sud. 832,000 mt/y LPG plant planned.
Hassi Messaoud Nord. 485,000 mt/y LPG plant planned.
Rhourde Chouff. 7 MM cu m/d gas gathering and conditioning under construction. Engr/ Design: Snamprogetti. Completion: 1994.
ARGENTINA
YACIMIENTOS PET. FISCALES. Campo Curan. 300 MMscfd and 250 MMscfd of LPG expansion under construction. Design/Engr: Fish Engr. Completion: 1992.
AUSTRALIA
SAGASCO. Beharra Springs, WA. 20 MMcfd plant under construction. Engr: Davy John Brown. Completion: 1992.
WOODSIDE OFFSHORE PETROLEUM ptl. Withnell Bay, Burrup Peninsula (near Karratha). 2 MM mt/y LNG train No. 3 in design stage. 6 MM mt/y LNG total capacity. Engr/Contr: Kellogg/JGC. Completion: 1993.
BANGLADESH
BAKHRABAD GAS SYSTEMS Ltd. Feni gas field. 40 MMscfd solid desicant gas dehydration plant planned.
PETROBANGLA. Kailashtilla. 5,000 mt/y LPG plant under construction. Contr: Penspen. Completion: 1992.
BOLIVIA
YPFB. Viboras. 1 MM cu m/d gas treating plant under construction. Contr: McKee Del Plata SA. Completion: 1993.
BRAZIL
PETROBRAS. Rio Grande Do Norte. 38.8 MMcfd gas processing plant planned. 152,100 gpd LPG, 26,900 gpd C5. In-house. Completion: January 1995.
CANADA
AEC OIL AND GAS. Alta. *Booster compression addition (4,000 hp turbine) at the Suffield Koomati Station. Completion: November 1992.
DOW CHEMICAL. Fort Saskatchewan. *NGL fractionation plant. $120 MM.
SHELL CANADA. Caroline, Alta. 300 MMcfd expansion under construction. $950 MM. Engr/Contr: Delta Projects Inc./Petrotech Lavalin. Completion: 1993.
TOTAL PETROLEUM CANADA Ltd. Spirit River, Alta. Lo-cat hydrogen sulfide oxidation process unit. Contr: Colt Engineering.
CHINA
Shenzhen City, Guangdong. $150 MM processing complex. Capacities will be 86,200 mt/y LPG, 70,000 mt/y polypropylene, 100,000 mt/y gasoline.
ARCO CHINA, Inc. *400 MMscfd offshore gas processing plant to process Yacheng 13-1 production for Hong Kong and Hainan Island. 60 MMscfd gas plant and condensate facilities onshore at Hainan Island. Design: Brown & Root, Completion: 1995.
CHINA NATIONAL TECHNICAL IMPORTS Corp. Puyang. 75 MMcfd NGL recovery plant in the engineering stage. Engr: CTIP.
CHINA, HONG KONG
HONG KONG AND CHINA GAS Co. Tai Po. 1,400 cu m/d expansion of British Gas gas process under construction. Contr: Babcock. Completion: 1992.
COMMONWEALTH OF INDEPENDENT STATES
(formerly U.S.S.R.)
GAS PROM. Novy Urenval. 250 MMcfd gas processing plant in the engineering stage. DD/Proc/Engr/Contr: John Brown,
MACHINOIMPORT. Tenguiz II & III. Natural gas and oil treatment plant including 2 Claus plants under construction. Inlet separation, acid gas removal, and produced water treatment. Contr: Lurgi/Partec Lavalin/Litwin. Completion: 1992/1993.
SOVIET MINISTRY OF OIL REFINING AND PETROCHEMICAL INDUSTRY. Surgut and Tobolsk. Gas processing plants. $10 billion. Feasibility study: Combustion Engineering: McDermott International, Mitsubishi, Mitsui. Completion: Late 1990's.
DENMARK
DANISH OIL NATURAL GAS. Stenlille. dehydration unit and preheater unit with 127 MMscfd each in the engineering stage. Design/Engr/Contr: John Brown.
NORSK SHELL. Sola. *Expansion of TIP Kero Merox.
EGYPT
BADR PETROLEUM. Western Desert. 90 MMscfd gas/oil separation compressor in the engineering stage. Engr: Bechtel. Completion: 4th Qtr. 1992.
EGYPTIAN GENERAL PETROLEUM Co. Ameriya. 250 MMscfd LPG plant in engineering stage. 194 mt/d PLG, 1,037 b/d gasoline and 19 MMscfd C2/C3 Mix.
Transgulf. 65 MMscfd gas gathering system in engineering stage. Completion: 1994.
NIDOCO. Elqar'a. 190 MMscfd gas gathering and conditioning plant under construction. 180 mt/d LPG, and 6,115 b/d gasoline. Design: Snamporgetti, Completion: 1992.
WESTERN DESERT OPERATING PETROLEUM Co. North Abu. Qir. Phase two of a 60 MMscfd gas gathering plant under construction. Design: ENPPI. Completion: 1992
GERMANY
BEB ERDGAS u. ERDOL GmbH. Soltau, Sohlingen. 16.95 MMscfd LTS unit and cold fractionator unit in the engineering stage. Engr: DSD Dillinger Stahlbau.
Friedrichseck. 4-LTS units each at 35.32 MMscfd in the engineering stage. Engr: DSD Dillinger Stahlbau.
Manslagt Platform. 35.32 MMscfd dehydration unit in the engineering stage. Design/Engr/Contr: DSD Dillinger Stahlbau.
DEA MINERALOL AG. Hemsbunde, Bodersen. 16.95 MMscfd LTS unit in the engineering stage. Design/Engr/Contr: DSD Dillinger Stahlbau.
HULS AG. Marl. *1.6 MMscf/hr hydrogen plant. $21 MM. Contr: Uhde.
STATOIL. Etzel. 2-dehydration units at 508 MMscfd each in the engineering stage. Design/Engr/Contr: DSD Dillinger Stahlbau.
WINTERSHALL KASSEL. Olbernhau. 2-dehydration units at 296 MMscfd each in the engineering stage. Design/Engr/Contr: DSD Dillinger Stahlbau.
INDIA
GAS AUTHORITY OF INDIA Ltd. Auraiya, Uttar Pradesh. $1,380 MM separation plant planned.
Bijaipur, Madhya Pradesh. gas processing plant to recover 8,000 b/d LPG.
Guna, Madhya Pradesh. $490 MM gas processing plant planned.
IBP Co. Ltd. Gujarat, Assam. 122,410 mt/y of LPG and other products will be produced at three plants, Gandhar and Batoda, Both in Gujarat and Lakwa, Assam.
MADRAS REFINERIES Ltd. Thanjavur district. 10,000 b/d gas processing plant to handle crude and associated gas from Cauvery basin fields.
OIL & NATURAL GAS COMMISSION. Gandhar and Mehsana, Gujarat; Lakwa, Assam; offshore Krishna-Godavari basin; Agartaia basin, Tripura. five gas processing plants. 500,000 mt/y LPG.
INDONESIA
ATLANTIC RICHFIELD BALI NORTH Inc. Jakarta. 250 MMscfd gas processing plant in the construction stage. Contr: P.T. Patrosea. Completion: August 1993.
ATLANTIC RICHFIELD INDONESIA Inc. Jakarta. 114 MMscfd offshore Bravo 2 compression & CO2 removal in the engineering/construction stage. Completion: End 1993.
*210 MMscfd offshore ONWJ gas handling/dehydration facilities in engineering/construction stage. Contr: P.T. McDermott. Completion: August 1993.
EXXON PRODUCTION. Natuna Is. LNG plant in the engineering stage. Engr: Bechtel. Completion: 4th Qtr. 1995.
IRAQ
TECHCORPS. Mussayyib. *27,500 b/d C3. Contr: IFP. Completion: 1993.
ITALY
ICIP. Ligure. *0.85 MMcfd hydrogen plant under construction. Contr: KTI. Completion: 1992.
MONTE FLUOJ. Bussi. *1.5 MMcfd hydrogen plant under construction. Contr: KTI. Completion:L 1992.
SADIO. Mantova. *1.3 MMcfd hydrogen plant under construction. Contr: KTI. Completion: 1992.
KOREA
KOREA GAS Corp. Inchon, South Korea. 3 MM t/y LNG receiving terminal in the engineering stage. Lic: Kellogg. Engr: Kellogg/Hyundai. Contr: Hyundai. Completion: 1995-96.
LIBYA
AGIP Ltd. Bu Attifel. 11 MM std cu m/d NGL recovery and 3,500 b/d of condensate under construction. Engr/Design/Contr: Snamprogetti. Completion: 1993.
MALAYSIA
PETRONAS. Bintulu. 100 MMcfd gas processing plant. $750 MM. (Joint venture with Royal Dutch/Shell). Planning. Yield 12,000 b/d.
MEXICO
FMC Corp. Santa Clara. *0.75 MMscfd hydrogen plant in the engineering stage. Contr: Howe-Baker. Completion: 1993.
PETROLEOS MEXICANOS. Matapionche, Ver. 150 MMcfd cryogenic expander under construction. Completion: 1992.
NETHERLANDS
AMOCO NETHERLANDS PETROLEUM Co. Offshore. 500 MMcfd gas production facility. Completion: 1993.
NEW GUINEA
PHILLIPS PETROLEUM. *LNG plant in the engineering stage. Engr: Bechtel. Completion: 4th Qtr. 1995.
NEW ZEALAND
SHELL BP AND TODD OIL SERVICES Ltd. Maul, Taranaki. C6+ expansion. Products: 43,804 g/d LP mix, 21,400 g/d condensate. Completion: January 1993.
NIGERIA
NIGERIA LNG Ltd Benny Island. 4 MM tons LNG. Completion: Early 1995.
River State. LNG plant planned. Lic: Technip/Snamprogetti. Engr: Kellogg.
NIGERIAN AGIP OIL Co. Ltd. Obiafu and Obrikom. 1,600 mt/d gas processing plant under construction. $40 MM. Contr: Randall. Completion: 1st Qtr. 1993.
PAKISTAN
OIL & GAS DEVELOPMENT Corp. Lashari field. 30 MMscfd gas dehydration unit. TEG process.
Pirkoh field. 100 MMscfd gas dehydration unit. TEG process.
SUI SOUTHERN GAS CO. LTD. Sui fields. Balochistan. *2-120 MMscfd gas purification and dehydration plants planned. (MEA & TEG absorption). $62 MM. Completion: June 1994-1995.
District Hyderabad. Badin Gas fields. *275 mt/d LPG recovery plant. Cryogenic expansion planned. $33 MM. Completion: December 1994.
PAPUA NEW GUINEA
CHEVRON OIL. Kutubu field. gas/oil separator in the engineering stage. Engr: Bechtel. Completion: 1993,
PHILLIPS PETROLEUM. LNG plant in the engineering stage. Engr: Bechtel. Completion: 1992.
PERU
PETROLEOS DEL PERU. Aguaytia. 30 MMcfd gas, 700 b/d LPG, 600 b/d gasoline, and 800 b/d kero-diesel plant. Bidding. Completion: 1993.
Camisea-Cuzco. 1,200 MMcfd plant. 24,100 b/d LPG, 14,400 b/d gasoline, 10,100 b/d naphtha and 5,100 b/d kerosene plant. $1,300 MM. Completion: 1995.
QATAR
NATIONAL OIL DISTRIBUTION. Umm-Said. 10,000 b/d fractionation of heavy condensate (from North Gas field) in engineering stage.
SPAIN
ENAGAS. Barcelona. LNG terminal revamping under construction. Design/Engr: Tecnicas. Completion: 1992.
Huelva. LNG terminal jetty expansion in the engineering stage. Detail/Engr: Tecnicas. Completion: 1992
SOLVAY. Torrelavega. *2.1 MMcfd hydrogen plant under construction. Contr: KTI. Completion: 1992.
SWEDEN
NYNAS ENERGY & CHEMICA'S COMPLEX. Nynasnamn. Texaco-gasification, gas treatment facilities in the engineering stage. Design: Uhde. Completion: 1993.
TUNISIA
BG TUNISIA, Hannibal. *New gas plant in the engineering stage. Process Design/Engr: Bechtel. Completion: 2nd Qtr. 1995.
UNITED KINGDOM
AMOCO U.K. EXPLORATION Co. Offshore. 2,200 MMscfd gas dehydration platforms. Completion: 1993.
BREMER VULKAN/GOLOR NOR. 80 b/d process facilities in the engineering stage. $100 MM. Engr: Lummus. Completion: 1993.
BRITISH GAS. Barrow Cumbria. 500 MMcfd gas processing plant in the engineering stage. $1,000 MM. DD/Proc Engr/Contr: John Brown. Completion: August 1993.
CONOCO. Theddlethorpe. 290 MMscfd gas processing plant under construction. $110 MM. DD/Proc Engr/Contr: John Brown. Completion: August 1993.
ENRON GAS PROCESSING (U.K.) Ltd. Seal Sands on Teesside. 400 MMcfd gas processing plant. 25 MM. Contr: Costain Engr.
HAMILTON OIL Co. Ltd. N. Wales. 250 MMscfd gas processing plant in the design stage. Design/Engr: Parsons Co.
MOBIL NORTH SEA Ltd. St. Fergus, Scotland. Four gas processing plants at 1,150 MMscfd in the design stage. Design/Engr: Parsons.
VENEZUELA
CORPOVEN SA. Anzoategui. 400 MMcfd expansion for gas processing capacity.
Santa Barbara, Montaga. 400 MMcfd cryogenic gas separation plant. Contr: Technip.
VIET NAM
PETROVIETNAM. Vung Tao. *(Joint venture with Petroleum Authority of Thailand Mitsui & Co. - 70% owned) 10.5 bcf/year new gas processing plant. $140 MM.
YEMEN
YEMEN HUNT OIL CO. 400 MMcfd gas processing plant under construction.
400 MMcfd expansion of gas processing plant in the engineering stage.
300 MMcfd gas processing plant in the engineering stage.
Copyright 1992 Oil & Gas Journal. All Rights Reserved.