PIPELINING - WORLDWIDE CONSTRUCTION

April 15, 1991
*Designates projects listed for the first time in the Journal. AMOCO PIPELINE CO. 19 miles, 8 in. trunk line replacement in Oklahoma. (A9) 8 miles, 8 in. trunk line replacement in North Dakota. (A9) 5 miles, 4 in. and 5 miles, 8 in. gathering line replacement in Texas.(A9) 3 miles, 8 in., 10 miles, 12 in. and 1.5 miles, 26 in. trunk line replacements in Texas. (A9) *CAJON PIPELINE CO. 122 miles, 20 in line from offshore California and San Joaquin valley oil fields to the Los Angeles basin.

*Designates projects listed for the first time in the Journal.

U.S. CRUDE LINES

AMOCO PIPELINE CO. 19 miles, 8 in. trunk line replacement in Oklahoma. (A9)

8 miles, 8 in. trunk line replacement in North Dakota. (A9)

5 miles, 4 in. and 5 miles, 8 in. gathering line replacement in Texas.(A9)

3 miles, 8 in., 10 miles, 12 in. and 1.5 miles, 26 in. trunk line replacements in Texas. (A9)

*CAJON PIPELINE CO. 122 miles, 20 in line from offshore California and San Joaquin valley oil fields to the Los Angeles basin. Completion: Early 1993.

CELREON CORP. 11 miles, 24 in. line from Gaviota, CA. to LasFiores, CA. under construction. (00)

PERMIAN OPERATING LTD. PARTNERSHIP. 13 miles, 6 in. from Dolphin field, divide county, ND, southeast to an Amoco pipeline in burke county, ND (A9)

SUN REFINING & MARKETING. 8.4 miles, 2-3 in. line from various lease connections Oklahoma gathering system. Contr: Mid-Continent Pipe Line Co. (00)

TRANS MOUNTAIN OIL PIPE LINE CORP. 144 miles, 36 in. crude line from Low point, WA to Anacortes & Ferndale, WA Proposed. Completion: Late 1993.

105 miles, 24 in. crude line from Burlington, WA to Low point, WA. Proposed. Completion: Late 1993.

U.S. PRODUCT LINES

AMOCO PIPELINE CO. 2 miles, 18 in. trunk line replacement in Texas. (A0)

20.6 miles, 12 in. trunk line replacement in Missouri. (A0)

CENEX. 246 miles, 8 in. line from Minot, ND to Fargo, ND to connect with the Williams pipe line system. Completion: Spring 1992,

COLONIAL PIPELINE CO. 45 miles, 12 in. line from Bainbridge, GA to Lloyd, FL Completion: Spring 1991.

COASTAL CORP. 40 miles, 8 in. line near Markham,TX. (A1)

*DIAMOND SHAMROCK R & M CO. 100 miles, 6 in line from Three Rivers, TX to 10 miles north of Laredo, TX. Completion: June 1991.

EXPLORER PIPELINE. 28 in. mainline expansion from Gulf Coast to Dallas-Fort Worth area under study. (A0)

U.S. GAS LINES

ARKLA ENERGY RESOURCES. *143.3 miles, 42 in from latimer county, OK to hot springs county, AR. (A1)

*77.5 miles, 36 in from latimer county, OK to hot springs county, AR. (A1)

*10 miles, 24 in from ozark to MRT west point compression station. (A1)

AMERICAN PIPELINE. 38 miles, 16 in. in East Texas to connect Union Pacific Resources Carthage gas processing plant with pipelines to the West. (A9)

ANR PIPELINE. *18.2 miles, 8 in. lateral in northern Wisconsin. Completion: 1991.

*25 miles, 30 in. looping in northern Wisconsin. Completion: 1991.

*14 miles, 30 in. looping in eastern Wisconsin. Completion: 1991.

*9.5 miles, 42 in. looping in northern Indiana. Completion: 1991.

CHAMPLAIN PIPELINE CO. 253 mile line from Highgate, VT, to Medway, Mass. $354 MM. Planned. (A9)

CMS GAS TRANSMISSION CO. 25 miles, $6.5 million gas pipeline in otsego, crawford, and kalkaska counties, MI Filed with Michigan Public Service Comm. (00)

CNG Transmission Corp. 47 miles, 20 in. line from kanawha county, WV to wyoming county, WV. Completion: 1992.

7 miles, 24 in. line from prince william county, WV to fauquier county, VA. 1991.

COASTAL CORP. (joint venture with Arkla Inc.) 1000 miles, 30 in. Wyoming-California Pipeline Co. gas system. planned. (A0)

COLORADO INTERSTATE GAS CO. 223 miles, 20 in. line from eastern Utah through northwest Colorado to its main system is southwest Wyoming. Proposed. (A1)

COLUMBIA GAS TRANSMISSION CORP. 5.1 miles of 24 in. in lancaster county, PA before FERC. Completion: Nov. 1991.

7.2 miles, 24 in. in fayette and greene counties, PA. FERC approved. Completion: Nov. 1991.

7.3 miles, 24 in. in lancaster county, PA. Completion: Nov. 1991.

14.2 miles, 24 in. in albemarle, louisa, goochland & chesterfield counties, VA. Before FERC. Completion: Nov. 1991.

5.8 miles, 36 in. in hardy county, WV. Before FERC. Completion: Aug. 1992.

5.9 miles, 24 in. in rockland county, NJ, FERC approved. Completion: July 1991

*2.3 miles, 36 in piedmont project, from clay county, WV to randolph county, WV. Before FERC. Completion: Aug. 1991.

*1.4 miles, 36 in piedmont project from clay county, WV to randolph county, WV. Before FERC. Completion: July 1992.

COLUMBIA GULF TRANSMISSION CO. 20.3 miles, 16 in. line from West Cameron 485 to East Cameron 313. planning. Completion: July 1991.

*3.4 miles, 20 in. Erath lateral segment of east lateral system, vermilion parish, LA. Planning. Completion: July 1991.

*CONOCO INC. 21 miles, 10 in Grand Isle project.

DELTA PIPELINE CO. 190 miles, 24 in from eastern Oklahoma to western Arkansas. Completion: Fall 1991.

EASTERN AMERICAN STATES TRANSMISSION. (Coastal Corp.). 285 miles, 30 in. from Ohio to Pennsylvania and 76 miles, 24 in. from New York to Long Island. Before FERC. (A9)

EL PASO NATURAL GAS. 14.8 miles, 30 in. loop line from Mohave Companion Project to transmission loop in Arizona. $10.8 MM. Before FERC. Completion: Mid 1992.

26 miles, 30-34 in. from coal steam project to transmission loops in New Mexico. $23 MM. Before FERC. Completion: Mid 1991.

12.96 miles, 30 in. from Wenden to Ehrenberg to transmission loops in Arizona. Before FERC. Completion: Mid 1991.

187.6 miles, 34 in. and 50.4 miles, 36 in. from OEC-Mojave project to transmission loops in county, NM and AZ. Before FERC. Completion: Mid-1992.

EMPIRE STATE PIPELINE. (Coastal Corp. and Union Enterprises. Ltd.) 155 miles, from Niagara Falls to Syracuse to connect with Union Gas Ltd's Canadian system. $85 MM. Proposed. Completion: Fall 1991.

ENDEVCO INC. 240 miles, 20-24 in. from Shreveport, LA to south central Mississippi. (joint venture with Bass family interests of Fort Worth) $95 million. Completion: Winter 1991-92.

44 miles, 24 in line from Delhi, LA to Vicksburg, MS Planned.

19 miles, 12-8 in line in smith and simpson counties, MS

ENRON CORP. Filed with FERC for an expansion of it's eastern leg from Ogden, IA to near Janesville, WI Completion: 1992.

*30 in. line across the Mississippi river. (A1)

FLORIDA GAS TRANSMISSION. *40 miles, 24 in. rehabilitation project in Mississippi and Florida. Completion: May 1991.

4 miles, 6 in. line from orange county, FL to Disney World. Completion: Sept. 1991.

36 miles, 18 in. line from hillsborough county, FL to manatee county, FL. Completion: May 1992.

GATEWAY PIPELINE CO. (United Gas Pipe Line). 25 miles, 30 in. line to connect existing and planned gas treatment plants in Mobile County, AL to United's Lirette, LA to Mobile, AL line. Before FERC. (A9)

GREAT LAKES GAS TRANSMISSION CO. *25.4 miles, 36 in Houghton Lake, MI. Completion: Dec. 1991.

INTERCON GAS INC. 77 miles, 6 in. line from near Festus, MO. to Rolla, MO. Completion: Late 1991.

JUBILLE PIPELINE SYSTEM. 100 miles, 8-24 in. Various offshore blocks in Mobil area Bayou La Batre. Planned. Completion: 1991.

KERN RIVER GAS TRANSMISSION CO. (Williams Cos. and Tenneco). 904 miles, 36 in. from Opal, WY to Bakersfield, CA. $800 MM. FERC final certificate issued. Completion: Dec. 1992.

*81 miles, 36 in from Beaver, UT to Veyo, UT. Completion: May 1991.

*61 miles, 36 in from Evanston, WY to Salt Lake City, UT. Completion: May 1991.

MAGNOLIA PIPELINE CO. (Basin Pipeline Corp. and a unit of Transco Energy Co.) 55 miles intrastate line, 40 miles of laterals from Alabama's Black Warrrior basin to Transco's interstate line in Central Alabama. $55 Million. (A0)

MISSOURI PIPELINE CO. 22 miles of 12-16 in. line from Curryville, MO to St. Charles and West Alton, MO $15 MM. (09)

Converting 70 miles of existing crude line to gas line in Pike, Lincoln, and St. Charles counties, MO. (A0)

NORTHERN BORDER PIPELINE. 368 miles, 30 in. mainline extension from Ventura, JA to Tuscola, IL. Before FERC. $374 MM. Completion: Fall 1992.

NORTHERN NATURAL GAS. 25 miles, 16 in. branch line in Madison, WI. Contr: Sovde Bros. Completion: 1991.

NORTHWEST PIPELINE CORP. *612 miles of pipeline loops in Orgeon, Washington, Idaho, Wyoming, Colorado and New Mexico. Completion: Jan. 1993.

PACIFIC GAS TRANSMISSION. 430 miles, 42 in. from Kingsgate, B.C., to Malin, OR $1 billion. Before FERC. Project manager: Bechtel. Completion: Nov. 1993.

294 miles, 42 in. and 120 miles, 36 in. from Malin, OR to Kern River Station, CA. Before CPUC. Project manager: Bechtel. Completion: Nov. 1993.

PHILLIPS PIPELINE CO. 324 miles, 10 in. from Midland, TX to Sweeney, Tx. Design: Gulf Interstate. Completion: Oct. 1991.

SEAGULL ENERGY CORP. 73 miles, four pipelines from Deer Park, TX to Mont Belvieu, TX.(A0)

SEMCO PIPELINE CO. 18.1 miles, 18 in. line from Columbus, MI to Greenwood, MI. Contr: H.L. Crouse. Completion: May 1991.

SOUTHERN CALIFORNIA GAS CO. 5.1 miles, 26 in. line 765 from Compton to Salt Lake. Planning. Completion: Aug. 1991.

6.5 miles, 26 in. line 765 Glendale to Los Angeles. Planning. Completion: Nov. 1991.

23.48 miles, 20 in. line 7000 tipton hwy. to line 504 west of Visalia. planning. June 1991.

SOUTHERN NATURAL GAS CO. 81.3 miles, 20 in. from Winn parish, LA to Concordia parish, LA. Planning. Completion: Oct. 1991.

55.1 miles, 24 in. and 36 in. Mobil Bay Pipeline. (Mobil Co., AL) FERC filing. Completion: Dec. 1991.

TENNECO INC. AND CITRUS CORP. (joint venture) 53 miles, 36 in. line from Mobile Bay off Alabama north to an interconnection with Florida Gas Transmission Co. Before FERC. (A9)

TENNESSEE GAS PIPELINE CO. 31.4 miles, 30 in. near Buffalo, NY. Completion: Dec. 1991.

TENNESSEE RIVER INTRASTATE CO. (with Champion International Corp.) 38 mile line to Courtland, AL. (09)

TEXAS EASTERN TRANSMISSION (joint venture with ANR Pipeline) 204 miles, 30 in. line from existing and proposed gas processing plants in Mobile county, AL., northwest to Texas Eastern's main line in Kosciusko, MS. $153.3 MM. Before FERC. (A9)

(Texas Eastern only) 55 mile, 24 in. offshore line from Mobile county, AL and future offshore production facilities in the Norphlet trend southwest to a proposed Viosca Knoll extension of the company's Main Pass pipeline system. $72.5 MM. (A9)

TEXAS GAS TRANSMISSION CORP. 62.4 miles, 36 in. line from Daviess county, KY to Warren county, OH. Completion: 1991.

69 miles, 30 in. from Bolivar county, MS. to Lincoln county, AR. Completion: 1991.

26.4 miles, 36 in. line from Ohio county, KY to Dearborn county, IN. Completion: 1992.

21.1 miles, 24 in. line in Claiborne parish, LA. Completion: 1991.

5.7 miles, 30 in. line from Hopkins county, KY. to Muhlenberg county, KY. Planned. Completion: 1991.

5.4 miles, 20 in. line in Muhlenberg county, KY. Planned. Completion: 1991.

TRANSCONTINENTAL GAS PIPELINE CO. 23.94 miles, 36 in. loops in Monroe and Luzerne counties, PA. Contr: Murphy Bros. (00)

48 miles, 12-30 in. from Edison to Riverdale, NJ. Contr: Napp-Grecco Corp. (00)

5 miles, 36 in. in Morris and Essex counties, NJ. Contr: Otis Eastern Services Inc. (00)

*9.4 miles, 10 in. line on High Island. (A1)

*12.2 miles, 16 in. line on Mustang Island. (A1)

TRANSTEX GATHERING SYSTEM *40 miles, 12 in. from High island blocks A69 to block A109. (A1)

TRANSWESTERN PIPELINE CO. *98 miles, 30 in. San Juan pipeline from Farmington to Gallup, NM. Completion: Dec. 1991.

*200 miles, 30 in. transwestern loops - 5 sections of approx. 40 miles each. Completion: Dec. 1991.

VIRGINIA NATURAL GAS. 80 miles, 24 in. and 40 miles, 10 in. from Richmond, VA to James City county, VA. Completion: 1991.

WYCAL-Wyoming-California Pipeline Co. (Coastal Corp.). 1,000 miles, 30 in. from Rocky Mountain Overthrust Belt, southwest Wyoming to near Bakersfield, CA. FERC final certificate issued. $665 MM. Completion: Late 1991.

ALGERIA

300 mile gas line from Hassi R'Mel gas field in Algeria to the Moroccan border. Proposed. Completion: 1995.

AUSTRALIA

GAS & FUEL CORP OF VICTORIA. 5 miles, 6 in. natural gas line from Kyabram to Tongala planned. Completion: July 1991.

*19 miles, 6 in. gas line from Kyabram to Echuca. Contr: Minson Constructions Pty. Ltd. Completion: Jan. 1992.

*62 miles, 6 in. gas line from Allansford to Portland. Feasibility study. Completion: Jan. 1992.

*10 miles, 8 in. gas line from Allansford to Portland. Feasibility study. Completion: Jan. 1992.

MAGELLAN PETROLEUM CORP. 375 mile gas line from the Amadeus-Darwin pipeline to the Nabalco bauxite mine and alumina refinery at Gove. Contr: Nabalco Pty. Ltd. (A1)

BANGLADESH

BANGLADESH OIL, GAS AND MINERALS CORP. 117 miles, 20 in. gas line from Kailashtila to Ashanganj. Design stage. Consulting: Pencol. Completion: 1991.

TITAS GAS. 78 miles, 24 in. and 61 miles, 12 in. line from a gas field near Ashunganj to a fertilizer plant near Tarakandi. Contr: Spie Capag. Completion: June 1991.

BELGIUM

DISTRIGAZ. 91 miles, 40 in. gas line from Zeebrugge (Dudzele) to Blaregnies (Quevy) under study. Completion: 1992-1993.

*65 miles, 16 in. gas line from Berneau to Bastogne under study. Completion: 1993.

CANADA

ALTAMONT PROJECT. (Amoco Canada Ltd., Canadian Occidental Petroleum Ltd., Esso Resources Canada Ltd., Home Oil Ltd., Mobil Oil Canada Ltd, Petro-Canada, and Shell Canada Ltd.) $1 billion gas line from Alberta to California. Proposed. (A9)

FOOTHILLS PIPELINES (YUKON) LTD. 1,429 miles of gas line from the Arctic Coast near Inuvik, North West Territory to Caroline in Central Alberta to connect with existing North American pipeline systems. $4.4 billion. Before NEB. Completion: 1996.

PACIFIC COAST ENERGY CORP. (joint venture of Westcoast Energy and Chieftain Development) 330 miles, 10 in. line from British Columbia to Vancouver Island. $506 MM. Contr: Intec Engin. Inc. Completion: May 1991.

118 miles, 101/4 in. Mainland portion of the Vancouver Island pipeline project. Contr: Majestic Contr. Ltd. (00)

186 miles, 4-10 in. gas line from Victoria, B.C. to Campbell river, B.C.. Contr: Banister Pipeline. Completion: Sept. 1991.

PACIFIC GAS TRANSMISSION CO./PACIFIC GAS & ELECTRIC. 900 miles, 36-42 in. gas line from the British Columbia-Idaho border to San Francisco Bay area in the detailed design phase. Completion: 1993.

120 miles, 36 in. gas line from the San Francisco Bay area to Fresno county. Completion: 1993.

PETROLEUM RESOURCES LTD. 21 miles, sour gas pipeline near Calgary. $14 million. Approval received. (09)

POLAR GAS LIMITED. 1,450 miles, 36 in. from Canadian Mackenzie Delta Pipeline Project to Caroline, Alberta. Planned. Contr: Transcanada Pipelines Ltd./Tenneco Inc./Panarctic Oils Ltd. Completion: Nov. 1996.

POUCE COUPE PIPE LINE LTD. 16 miles of crude line connecting facilities built by Norcen Energy and Canadian Hunter in Northeast B.C. with Peace Pipe system in northwest Alberta. (00)

SHELL CANADA. 42 km liquid sulfur line in Caroline, Alberta in the engineering stage. Engr: Shawinigan. Contr: Petrotech Lavalin. Completion: 1991.

TRANSCANADA PIPELINES LTD. 110 miles, 48 in. gas line, Saskatchewan and Manitoba looping. Before NEB. Completion: Oct. 1991.

144 miles, 42 in. gas line, Manitoba and northern Ontario looping under construction (90/91 winter). Completion: April 1991.

144 miles, 42 in. gas line, Manitoba and northern Ontario looping (summer 1991). before NEB. Completion: Oct. 1991.

140 miles, 42 in. gas line, Manitoba and northern Ontario looping (91/92 winter). before NEB. Completion: April 1992.

133 miles, 42 in gas line, Manitoba and northern Ontario looping (summer 1992). before NEB. Completion: Oct. 1992.

113 miles, 42 in. gas line, North bay shortcut looping (northeastern Ontario). before NEB. Completion: Oct. 1992.

22 miles, 12 in. gas line awaiting start, Napierville extension. Completion: April 1992.

9 miles, 36 in. gas line, Eastern Ontario looping. Before NEB. Completion: Oct. 1991.

205 miles, 48 in. gas line from Saskatchewan to Manitoba looping. Before NEB. Completion: Oct. 1992.

9 miles, 36 in. gas line, Dawn extension looping. Completion: Oct. 1991.

12 miles, 24 in. gas line, Blackhorse extension before NEB. Completion: Oct. 1991.

16 miles, 16 in. gas line, Gananoque extension before NEB. Completion: Oct. 1992.

15 miles, 20 in. gas line, Quebec looping. Completion: Oct. 1991.

TRANS MOUNTAIN PIPE LINE. 149 mile pipeline to refineries near Anacortes and Bellingham. (A1)

UNION GAS. 65.1 km, 48 in. gas line in south western ontario. Completion: 1991.

7.3 km, 26 in. gas line in south western ontario. Completion: Oct. 1991.

33.4 km, 16 in. gas line in south western ontario. Completion: Oct. 1991.

8.5 km, 12 in. gas line in south western ontario. Completion: 1991.

11.8 km, 12 in. gas line in south western ontario. Completion: Oct. 1991.

6.84 miles, 48 in. gas line in south western ontario. Completion: Oct. 1991.

30.2 miles, 48 in. gas line in south western ontario. Completion: Oct. 1991.

CHINA

CHINA NATIONAL OIL CORP. 180 mile, 426 mm crude line from Zhongyuan oil field to Luoyang, Henan, refinery. (09)

CHINA, TAIWAN

Chinese Petroleum Corp. *40 miles, 12-20 in. crude and product line planned in northern oil terminal. (A1)

*190 miles, 8-24 in. gas loop lines planned from Yungan to Tunghsiao. (A1)

COLOMBIA

ECOPETROL. 290 miles, 24 in. crude line from Vasconia to Covenas (Oleoducto Colombia). Completion: 1991.

17 miles, 8 in. product line from Guacari to Yumbo. (09)

PROMIGAS S.A. 373 miles, 20 in. and 2,459 miles, 24 in. gas line from Pajaro to Bogota under study. (09)

7 miles, 4 in. gas line from Main Gas Pipe Line to Montelibano planned. (09)

9.3 miles, 3 in, gas line from Main Gas Pipe Line to Corozal planned. (09)

12.4 miles, 4 in. gas line from Main Gas Pipe Line to Arjona planned. (09)

8.7 miles, 4 in. gas line from Barranquilla to Puerto Colombia planned. (09)

5.4 miles, 3 in. gas line from Main Gas Pipe Line to Galapa planned. (09)

CUBA

116 mile crude line linking the terminal at Matanzas on the northern coast east of Havana with a refinery at Cienfuegos on the southern coast (with Soviet assistance.) (A9)

DENMARK

DANSK OLIE OG NATURGAS. 7 miles, 12 in. gas line from Lynge to Hillerod. Under study. Completion: 1991.

14 miles, 12 in. gas line from Skjddelev to Aihus. Under study. (09)

5 miles, 12 in. gas line from Kalvebod to HCV power plant. Under study. (A9)

5 miles, 10 in. gas line to power plant in Aalborg. Under study. (A9)

*37 miles, 30 in. gas line from Stenlille (gas storage) to Torslunde under study. (A1)

ECUADOR

PETROLEOS DEL ECUADOR. 165 km., 6-8 in. gas line from La Libertad refinery to Manla. Contr: Techint. (A9)

FINLAND

NESTE OY. 26 mile extension of Nesty Oy's southern Finland gas line into greater Helsinki. Contr: E. M. Pekkinen Oy. Welding and fitting: Zarubezhjneftegasstroi (U.S.S.R.). $10 MM. (09)

FRANCE

GAZ DE FRANCE. (joint venture with Gas du Sudouest and Enagas) 44 miles, 24 in. gas line from Serrablo, Spain to Lacq, France. Completion: 1991.

GERMANY

EVG. 106 miles, 32-40 in. gas line from Vitzeroda to Gera planned. Contr: Arge PKM/PLE. Completion: End 1992.

MIDAS GmbH. (joint venture of Wintershall AG and OMV AG) 348 miles, 32 in. gas line from Rysum (near Emden) to Ludwigshafen. Completion: 1993.

GASVERSORGUNG SUDDEUTSCHLAND GmbH. 19 miles, 16 in. gas line from Pfullendorf to Nenzingen planned. Completion: Oct. 1993.

RUHRGAS AG. 153 miles, 48 in. gas line from Werne to Schluchtern planned. Contr: Pipeline Engineering GmbH. Completion: 1994.

40 miles, 40 in. gas line from Lauterbach to Vitzeroda planned. Contr: Pipeline Engineering GmbH. Completion: End 1992.

*15.5 miles, 24 in. gas line planned from Vinnhorst to Ahlten. Contr: Pipeline Engineering GmbH. Completion: End 1993.

*7.5 miles, 12 in. gas line planned from Bonn to Euskirchen. Contr: Pipeline Engineering GmbH. Completion: 1992/93.

*102.5 miles, 48 in. gas line planned from Achim to Salzwedel. Completion: End 1993. (joint venture with BEB Erdgas und Erdol GmbH).

*STATOIL DEUTSCHLAND GmbH. 44 miles, 42 in. gas line from Emden to Etzel. Contr: Mannesmann. Completion: Oct. 1993.

HUNGARY

*HUNGARIAN OIL & GAS TRUST. 58 miles, 24 in. gas line from Dorog to Gyor. Contr: Olajterv, Kvv. Completion: Dec. 1991.

* 70 miles, 28 in. gas line from Endrod to Kiskundorozsma to Roszke. Completion: Dec. 1991.

*18 miles, 10 in. gas line from Kormend to Szentgatthard. Completion: Dec. 1991.

INDIA

98 miles, 4-20 in. Bombay high offshore gas lift pipeline network. Contr: Snamprogetti. Completion: 1991.

OIL & NATURAL GAS COMMISSION. 15 miles, 24 in. products line for Hazira export terminal, under construction. Contr: Land & Marine (Inida) Ltd. Completion: May 1991.

OIL INDIA LTD. (Indian Oil Corp.) 826 mile petroleum products line from Kandla, Gujarat, to Bhantinda, Punjab. $240 MM. Completion: 1992.

INDONESIA

650 miles, 10-16 in. products line in the engineering stage in the Trans Java network. Completion: 1993.

IRAN

IGAT 2. 880 miles, 48-56 in. from Kangan gas field on the Persian Gulf to the Soviet Union. Contr: Saipem (will lay 20% of remaining pipeline). (A9)

NATIONAL IRANIAN OIL CO. 63 miles, 42 in. crude line from Gurreh to Taheri (Moharram project). Contr: Snamprogetti. Completion: 1991.

*1,139.6 miles, 12 in. product line from Arak to Malayer and Mamadan. (A1)

ITALY

ENICHEM ANIC SpA. 140 miles, 8-10 in. products line from Montedison Petro. complex (Ferrara) to Enichem Petro. complex (Ravenna) in progress. Contr: Snamprogetti. Completion: 1991.

SNAM SpA. 168 miles, 36-42 in. gas line from Tarvisio to Zimella in progress. Italian section of the U.S.S.R.-Italy Natural Gas Pipeline Expansion. Contr: Snamprogetti. Completion: 1991.

TRANSMEDITERRANEAN PIPELINE CO. LTD. 99 mile gas line from Cap Bon, Tunisia to Mazara del Vallo, Italy. AlgeriaItaly natural gas submarine pipeline expansion in progress. Contr: Snamprogetti. Completion: 1991.

KENYA

KENYA PIPELINES CO. LTD. 355 miles, 6-8 in. products line from Nairobi to Kisumu/Eldoret, western Kenya (extension of existing Mombasa to Nairobi pipeline) under construction. Contr: NKK Corp./Lavalin/Sogea. Completion: 1993.

KOREA

KOREA PETROLEUM DEVELOPMENT CORP. 541 miles, refined products trunkline system from refineries at Yosu and Onsan to Seoul. Completion: 1992.

LIBYA

416 miles, gas line from Al Brika to Khoms. (A0)

MALAYSIA

PETRONAS. 485 miles, 36 in. gas line from Kerieh on Malaysia's northeast coast to Singapore with branch lines to Kuala Lumpur and other large Malaysian cities. Total cost: $310 MM. Completion: Nov. 1991.

MEXICO

PEMEX.

37 miles, 24 in. crude line from Venta de Carpio to Tula under construction. (A1)

223.7 miles, 16 in. product line from CD. Madero to CD. Valles under construction. (A1)

31.0 miles, 16 in. gas line from Matapionche to Tierra Blanca, Ver. under construction. (A1)

*24 miles, 24 in. gas line from San Pablo to Cuemanco under construction. (A1)

*60 miles, 36 in. gas line from CD. Pemex to Atasta under construction. (A1)

*77.7 miles, 16 in. gas line from Palmillas to Toluca under construction. (A1)

*46.6 miles, 24 in. gas line from Venta de Carpio to Cuemanco under construction. (A1)

*15 miles, 18 in. product line from Salina Cruz refinery to Maritime terminal under construction. (A1)

MOROCCO

900 miles of gas line through Morocco to Tangier to a link across the Strait of Gilbralter to Spain. Proposed. Completion: 1995.

SOCIETE CHERIFIENNE DES PETROLES. 115 miles, 14 in. crude line from Port of Mohammedia to Sidi Kacen Refinery, in the engineering stage. Engr: OTP. Completion: 1992

THE NETHERLANDS

NV NEDERLANDSE GASUNIE. 19 miles, 48 in. gas line from Baigzand to Oud. tocht. planned. Completion: Oct. 1991. 12.5 miles, 12 in. gas line from Waalwyk to Kedichem planned. Completion: Nov. 1991.

34.5 miles, 24 in. gas line from Zuidwending to Witteveen. Completion: Jan. 1992.

*11.5 miles, 42 in. gas line from Ten Boer to Borgercompagnie. (A1)

*25 miles, 48 in. gas line from Witteveen to Ommen. Completion: Jan. 1992.

*12.5 miles, 36 in. gas line from Lintvelde to Winterswijk. Completion: Jan. 1992.

NAM. 161 miles, from F3 area of the Dutch North Sea to the Dutch Coast. (joint venture with Elf Petroland and Energie Beheer Nederland). Contr: McDermott-ETPM. Completion: 1991-92.

NIGERIA

NIGERIAN NATIONAL PETROLEUM CORP. 55 km, 16 in. Mogas/Gas oil product pipeline from proposed Bonny crude oil terminal to Port Harcourt refinery. Completion: June 1993.

55 km, 16 in. high pour fuel oil pipeline from proposed Bonny crude oil terminal to Port Harcourt refinery. Completion: June 1993.

47 miles, 14-18-24 in. gas line in progress. Escravos-Lagos gas pipeline project. Contr: Snamprogetti. Completion: 1991.

SHELL PETROLEUM DEVELOPMENT. 8 miles, 12 in. gas line from Cawthorne 1 flowstation to Alakiri gas plant. Planned. Completion: Jan. 1991.

14 miles, 12 in. gas line from Alakiri to Bomu. Planned. Completion: Jan. 1991.

7 miles, 8 in. crude line from Belema flowstation to Nembe Creek Cawthorne Channel trunkline. Planned. Completion: Dec. 1992.

43 miles, 20-24 in. crude line from Opukushi to Forcados terminal (Trans Ramos Pipeline). Planned. Completion: Dec. 1993.

6 miles, 8 in. crude line from Okpokonou flowstation to Southern Forcados Pipeline at Ogara Manifold. Planned. Completion: Dec. 1993.

6 miles, 8 in. crude line from Kanbo flowstation to Trans Ramos Pipeline at Kanbo Manifold. Planned. Completion: Dec. 1993.

NORWAY

STATOIL. 25 miles, 36 in. gas line from Zeepipe Sleipner to Statpipe. Eng: Snamprogetti. Planned. Completion: 1993.

524 miles, 30-40 in. gas line from Zeepipe Sleipner, Norway to Zeebruge, Belgium. (Zeepipe Natural Gas Transportation System -Phase 1) Engr: Snamprogetti. Completion: late 1993.

80 miles, 36 in. gas line from Zeepipe Troll to Heimdal. Planned. Completion: 1996.

95 miles, 40 in. gas line from Zeepipe Troll to Sleipner. Planned. Completion: 1996.

150 miles, 20 in. gas pipeline from Sleipner to Karsto. Planned. Completion: 1993.

OMAN

PETROLEUM DEVELOPMENT OMAN. 110 mile four pipeline gas system. Contr: Saipem/Consolidated Contr. Co. (A1)

PAKISTAN

PARCO. (Pak Arak Refinery Co. Ltd.) 865 miles, 16 in. product line from Lahore to Islamabad in the engineering stage. Completion: 1991.

PAPUA NEW GUINEA

CHEVRON NIUGINI PTY LTD. 105 miles, 20 in. crude line from Iagifu-Hedina field to export terminal. Contr: Spie Capag. Completion: Aug. 1992.

SOUTH PACIFIC CHEVRON CO. 40 miles, 6-18 in. gas and crude lines in Iagifu-Hedina. Contr: Bechtel. Completion: 1993.

PERU

PETROLEOS DEL PERU. 364 miles, 26 in.; 300 miles, 10 in.; 64 miles, 8 in. gas lines from Camisea-Cuzco to Callao-Lima. Bidding. Completion: mid 1993.

*52 miles, 6 in. gas and product line from Aguaytia to Pucalipa-Campo Verde. Completion: 1993.

*52 miles, 4 in. product line from Aguaytia to Pucallpa-Campo Verde. Completion: 1993.

*30 miles, 3 in. product line from Aguaytia to Pucallpa-Campo Verde. Completion: 1993.

PORTUGAL

280 mile line from Setubal south of Lisbon to Braga near the spanish border. Completion: 1993.

SAUDI ARABIA

SAUDI ARAMCO. 1,200 km, 56 in. crude line from Arabian Gulf to Yanbu (Red Sea) in the engineering stage. Contr: Mannesmann AG. Completion: End 1992.

*16 miles, 56 in. crude line on the east-west pipeline (loopline) incl. 11 pump stations. Completion: End 1992.

SINGAPORE

SHELL EASTERN PETROLEUM. 12 miles, 10 in. product line. Pandan products pipeline under construction. Contr: Bechtel. Completion: 2nd Qtr. 1991.

SPAIN

CAMPSA. 90 miles, 10 in. products line from La Coruna to Vigo under construction. Contr: Tecnicas Reunidas/Heymo. Completion: 1992.

60 miles, 10 in. products line from Cartagena to Alicante under construction. Contr: Tecnicas Reunidas/Heymo. Completion: 1992.

*63 miles, 8-12 in. product line from Barcelona to Gerona under construction. Contr: Tecnica Reunidas/Heymo. Completion: Mid 1991.

*130 miles, 8 in. product line from Almodovar to Merida (eastern Spain) planned. Completion: Late 1992 or early 1993.

EMPRESA NACIONAL DE GAS SA. 145 miles, 26 in. gas line from Sevilla to Brazatortas in engineering stage. Contr: Heymo. Completion: 1991.

44 miles, 24 in. gas line from Serrablo, Spain to Lacq, France. (joint venture with Gas de France and Gas du Sudouest). Contr: Heymo. Completion: 1991.

SWITZERLAND

GVM GASVERBUND MITTELLAND AG. 17 miles, 12 in. natural gas line planned. Contr: Helbling Engineering. Completion: End 1991.

7.5 miles, 12 in. gas line from Arlesheim to Prafteln in the engineering phase. Engr: Helbling and Jauslin & Stebler Engin. Completion: End 1992.

5 miles, 8 in. gas line from Lenzbrug to Villmergen in the engineering phase. Engr: Balzari & Schudel Engin. Completion: End 1992.

GVO GASVERBUND OSTSCHWEIZ AG. *5.5 miles, 10 in. gas line from Gossau to Bischofszell planned. Completion: End 1991.

SYRIA

AL FURAT PETROLEUM CO. 50 miles, 10-12-14 in. gathering lines in the engineering stage. Engr: Lavalin Int. Completion: Feb. 1992.

THAILAND

PETROLEUM AUTHORITY OF THAILAND. (PTT).

100.6 miles, 24 in. natural gas line from Erawan to Khanom district to Nakhon Si Thammarat Province planned. Completion: 1994.

106.3 miles, 32 in. natural gas line from PTT's 8 structure gas field to Unocal Thailand Ltd's Erawan field planned. Completion: 1993.

243.8 miles, 24 in. natural gas line from Namphong Khonkan Province to Saraburi Province planned. Completion: 1993.

121 miles, 32 in. gas line from offshore Texas Pacific field, Gulf of Thailand to Erawan field, Gulf of Thailand. Planned. Completion: 1992.

*6.6 miles, 8-12-16 in. natural gas line from National Petrochemical Co. to the factories in Mab Ta Pud estate in the design phase. Completion: 1992.

*118.8 miles, 20 in. product line from Sri Racha, Chonburi province to Saraburi province planned. Completion: 1994.

UNITED KINGDOM

ARCO BRITISH LTD. 41 miles, 24 in. and 5 miles, 16 in. gas line from Pickerill gas field (UK-southern north sea) to Theddlethorp (UK mainland) in the engineering stage. Completion: 1992.

BRITISH GAS CORP. 15.6 miles, 36 in. gas line from Easington to Paull. Planned. Completion: Aug. 1991.

BORD GAIS EIREANN. 45 miles, 30-36 in. gas line in Southwest Scotland in the engineering stage. Engr: John Brown. Completion: Sept. 1993.

BP EXPLORATION. 36 in. pipeline to serve Forties field in the U.K. North Sea. Contractor: ETPM Services (U.K.) Ltd. (09)

15 mile, 12 in. natural gas liquids pipeline linking Total Oil Marine plc's St. Fergus, Scotland, gas terminal to BP's Cruden Bay terminal. (A0)

CATS-Central Area Transmission System. (40% Gas Council Exploration Ltd., 30% Amoco UK Exploration, 18% Amerada Hess, 12% Texas

Eastern North Sea Inc.). 410 km, 36 in. gas line from Everest and Lomond fields to Teesside. $1.8 billion central U.K. North Seas gathering system. Contr: McDermott/ETPM. Completion: Aug. 1992.

ESSO PETROLEUM CO. 31 miles, 12 in. product line into Birmingham International Airport, England. Contr: John Brown. Completion: Sept. 1992.

MOBIL NORTH SEA LTD. 210 miles, 30 in. gas line from Beryl oil field in the U.K. North Sea to St. Fergus, Scotland. Contr: Brown & Root and Saipem. (A0)

SHELL CHEVRON U.K. LTD. 251 miles, 10 in. ethylene pipeline system linking the Stanlow and Carrington plants in northwestern England to Grangemouth under construction. $154 MM. Contr: Bechtel. Completion: Early 1992.

U.S.S.R.

MACHINOIMPORT. Tenqiz. 188 miles, various size pipelines.

Field gathering system to transport sour oil and gas from 100 wellhead sites to 4 locally situated refinery plants under construction. Contr: Lavalin Int. Completion: 1991.

ZAMBIA

TAZAMA PIPELINES LTD. 1,068 miles, 8 in. and 480 miles, 12 in. of crude pipeline from DarEs-Salaam, Tanzania to Ndola, Zambia. Contr: In-house. Completion: 1992.

ZIMBABWE

LONRHO PLC. 135 miles, 10 in. products line from Feruka to Harare (extension of Beira to Feruka pipeline). Study and conceptual design stage. Consulting: Pencol. Completion: 1991.

COMPANAI DO PIPELINE MOCAMBIQUE. 180 miles, 10 in. products line rehabilitation from Beira, Mozambique to Feruka, Zimbabwe. Contr: John Brown. (A1)

Copyright 1991 Oil & Gas Journal. All Rights Reserved.